Dynacor Advances Expansion Projects, Ecuador Plant Rehabilitation 65% Complete - Investing News Network
AI desk brief
Dynacor said its 1,500-tpd Ecuador plant rehabilitation is 65% complete and on schedule for first ore feed in October/Q4-2026, with initial gold pour also targeted for Q4-2026. As of Aug. 30, it had spent US$9.5m of the projected US$22-25m 2026 capex budget; the crushing circuit is 85% complete, the ball mill is finished, and the company has secured a 6-MW grid connection backed mainly by hydro power.
In Senegal, commissioning is complete at the 50-tpd plant and ramp-up is underway ahead of an inaugural gold pour. In Peru, Dynacor is reducing ore inventory, aiming to bring it to 75% of the historical average by quarter-end; management said the two expansion projects should materially add to 2027 production.